Hello all Techies..
I have worked with "Ifs" and "Ors" and "Ands" and "VLookups" but i understand i will need something with MACRO because the number of Subprojects vary on every project
We have some projects. These projects are sub-divided amoung Students based on the length of the project. There can be single subproject or multiple .. (but never seen more than 15) under one project
The Main Project can not be closed until all the sub-projects are closed
All (Project and Subproject) have a unique Numeric code assigned
My list will always have the project and subproject which might be in Red/Orange/Blue/Green State. Where Red is work not started, Orange means somewhere in between, Blue is others, Green means Good to close.
The list is endless and comes to me everyday. :eek:
I am looking for a Macro which will give me result in Cell of Column A corosponding to Main Project whether it is good to close stating Green.
The main project can only be closed if all the subprojects are Good to Close (Green)
Someone please help me out of this mess :(
Please find the attached sample file Status_Report.xlsx
Thanks
Pitamber
I have worked with "Ifs" and "Ors" and "Ands" and "VLookups" but i understand i will need something with MACRO because the number of Subprojects vary on every project
We have some projects. These projects are sub-divided amoung Students based on the length of the project. There can be single subproject or multiple .. (but never seen more than 15) under one project
The Main Project can not be closed until all the sub-projects are closed
All (Project and Subproject) have a unique Numeric code assigned
My list will always have the project and subproject which might be in Red/Orange/Blue/Green State. Where Red is work not started, Orange means somewhere in between, Blue is others, Green means Good to close.
The list is endless and comes to me everyday. :eek:
I am looking for a Macro which will give me result in Cell of Column A corosponding to Main Project whether it is good to close stating Green.
The main project can only be closed if all the subprojects are Good to Close (Green)
Someone please help me out of this mess :(
Please find the attached sample file Status_Report.xlsx
Thanks
Pitamber